Total Project Value (Revised CCE)
$876,462.55
Total Drawn to Date
$113,860.65
13.0%
Current Draw Amount
$113,860.65
Period ending March 16, 2026
Amount Remaining
$762,601.90
Balance in SOV categories

Project Details

DRAW 01 — Period ending March 16, 2026
Owner
Andrew & Cici Binns
8 Fletcher Ct, Breckenridge, CO
Project Address
8 Fletcher Ct, Breckenridge, CO
Financial Summary
Total Drawn to Date
$113,860.65
Total Paid to Date
$105,000.00
Amount Remaining in SOV
$762,601.90
Current Draw Amount
$113,860.65
Owner Paid Direct This Period
$0.00
Total Amount Currently Due
$8,860.65
Agreement & Schedule
Agreement Terms
Cost Plus 19% Contractor Fee
Contractor's Fee: 13%
Estimated Completion

Schedule of Values

Detailed breakdown by cost code — DRAW 01
Cost Code — Category CCE
2026-01-15
Changes
to Work
CCE
Revised
DRAW 01
2026-03-16
Drawn
to Date
%
Drawn
Remaining
in Categories
01 - SOFT COSTS & PRELIMINARY $6,950.00 - $6,950.00 $2,974.00 $2,974.00 43% $3,976.00
01.01 - Structural Engineering
$3,000.00 - $3,000.00 $2,974.00 $2,974.00 99% $26.00
01.02 - Printing Costs
$300.00 - $300.00 - - 0% $300.00
01.03 - Fire Department Fees
$150.00 - $150.00 - - 0% $150.00
01.04 - Permitting Fees
$3,500.00 - $3,500.00 - - 0% $3,500.00
02 - GENERAL CONDITIONS $82,431.00 $10,000.00 $92,431.00 $31,928.23 $31,928.23 35% $60,502.77
02.01 - General Labor
$37,700.00 - $37,700.00 $24,361.86 $24,361.86 65% $13,338.14
02.02 - Progress Cleaning
$6,000.00 - $6,000.00 $23.94 $23.94 0% $5,976.06
02.03 - Final Cleaning
$3,400.00 - $3,400.00 - - 0% $3,400.00
02.04 - Window Cleaning
$2,200.00 - $2,200.00 - - 0% $2,200.00
02.05 - Project Supervision
$20,000.00 - $20,000.00 $2,000.00 $2,000.00 10% $18,000.00
02.06 - Construction Waste
$4,900.00 - $4,900.00 $4,101.52 $4,101.52 84% $798.48
02.07 - Finish Material Protection
$2,000.00 - $2,000.00 $1,409.34 $1,409.34 70% $590.66
02.08 - Winter Conditions
$2,000.00 - $2,000.00 $31.57 $31.57 2% $1,968.43
02.09 - Project Liability Insurance
$4,231.00 $10,000.00 $14,231.00 - - 0% $14,231.00
03 - MASONRY $7,500.00 - $7,500.00 - - 0% $7,500.00
03.01 - Interior Stone Demo
$2,800.00 - $2,800.00 - - 0% $2,800.00
03.02 - Interior Stone Veneer
$2,200.00 - $2,200.00 - - 0% $2,200.00
03.03 - Stucco
$2,500.00 - $2,500.00 - - 0% $2,500.00
04 - METALS $1,500.00 - $1,500.00 - - 0% $1,500.00
04.01 - Structural Steel
$1,200.00 - $1,200.00 - - 0% $1,200.00
04.02 - Flashing
$300.00 - $300.00 - - 0% $300.00
05 - CARPENTRY $221,165.44 - $221,165.44 $20,578.51 $20,578.51 9% $200,586.93
05.01 - Rough Carpentry Materials
$4,300.00 - $4,300.00 $2,696.22 $2,696.22 63% $1,603.78
05.02 - Rough Carpentry Labor
$15,500.00 - $15,500.00 - - 0% $15,500.00
05.03 - Finish Carpentry Materials
$15,500.00 - $15,500.00 - - 0% $15,500.00
05.04 - Finish Carpentry Labor
$33,000.00 - $33,000.00 - - 0% $33,000.00
05.05 - Cabinetry
$70,000.00 - $70,000.00 - - 0% $70,000.00
05.06 - Cabinet Hardware
$2,500.00 - $2,500.00 - - 0% $2,500.00
05.07 - Bath Hardware
$600.00 - $600.00 - - 0% $600.00
05.08 - OPENINGS
$39,882.72 - $39,882.72 - - 0% $39,882.72
05.09 - Kitchen Bi-Fold | Hot Tub Bi-Fold | Hot Tub Window
$0.00 - $0.00 - - 0% $0.00
05.10 - Doors & Window
$29,832.72 - $29,832.72 $14,032.29 $14,032.29 47% $15,800.43
05.11 - Window
$3,850.00 - $3,850.00 $3,850.00 $3,850.00 100% $0.00
05.12 - Interior Doors
$3,200.00 - $3,200.00 - - 0% $3,200.00
05.13 - Door Hardware
$3,000.00 - $3,000.00 - - 0% $3,000.00
06 - FINISHES $204,016.68 - $204,016.68 - - 0% $204,016.68
06.01 - Drywall & Finish
$12,000.00 - $12,000.00 - - 0% $12,000.00
06.02 - Tile
$43,000.00 - $43,000.00 - - 0% $43,000.00
06.03 - Wood Flooring
$71,171.68 - $71,171.68 - - 0% $71,171.68
06.04 - Carpet
$12,000.00 - $12,000.00 - - 0% $12,000.00
06.05 - Interior Paint & Stain
$64,345.00 - $64,345.00 - - 0% $64,345.00
06.06 - Exterior Paint & Stain
$1,500.00 - $1,500.00 - - 0% $1,500.00
07 - SPECIALTIES $47,293.40 - $47,293.40 $26,643.40 $26,643.40 56% $20,650.00
07.01 - Great room and Master
$0.00 - $0.00 - - 0% $0.00
07.02 - Shower Enclosure
$5,700.00 - $5,700.00 - - 0% $5,700.00
07.03 - Wine Enclosure
$4,450.00 - $4,450.00 - - 0% $4,450.00
07.04 - Fireplaces
$26,643.40 - $26,643.40 $26,643.40 $26,643.40 100% $0.00
07.05 - Sauna
$10,500.00 - $10,500.00 - - 0% $10,500.00
08 - EQUIPMENT $24,798.21 - $24,798.21 - - 0% $24,798.21
08.01 - Appliances
$23,298.21 - $23,298.21 - - 0% $23,298.21
08.02 - Appliance Installation
$1,500.00 - $1,500.00 - - 0% $1,500.00
09 - COUNTERTOP & FURNISHINGS $36,500.00 - $36,500.00 - - 0% $36,500.00
09.01 - Stone Countertops
$32,000.00 - $32,000.00 - - 0% $32,000.00
09.02 - Window Treatments
$4,500.00 - $4,500.00 - - 0% $4,500.00
10 - PLUMBING & MECHANICAL $46,052.00 - $46,052.00 $11,050.00 $11,050.00 24% $35,002.00
10.01 - Plumbing / MECH System
$29,000.00 - $29,000.00 $11,050.00 $11,050.00 38% $17,950.00
10.02 - Plumbing Fixtures
$17,052.00 - $17,052.00 - - 0% $17,052.00
11 - ELECTRICAL $53,300.00 - $53,300.00 $5,952.50 $5,952.50 11% $47,347.50
11.01 - Electrical system
$18,300.00 - $18,300.00 $5,952.50 $5,952.50 33% $12,347.50
11.02 - Lighting Fixtures
$35,000.00 - $35,000.00 - - 0% $35,000.00
12 - COMMUNICATIONS & SECURITY $12,500.00 - $12,500.00 - - 0% $12,500.00
12.01 - Audio / Visual Connectivity
$6,000.00 - $6,000.00 - - 0% $6,000.00
12.02 - Audio / Visual Equipment
$4,000.00 - $4,000.00 - - 0% $4,000.00
12.03 - Security & Fire Alarm
$2,500.00 - $2,500.00 - - 0% $2,500.00
13 - EXTERIOR IMPROVEMENTS $1,240.00 $395.00 $1,635.00 $1,635.00 $1,635.00 100% $0.00
13.01 - Roof
$1,000.00 $395.00 $1,395.00 $1,395.00 $1,395.00 100% $0.00
13.02 - Garage Door
$240.00 - $240.00 $240.00 $240.00 100% $0.00
14 - ADDITIONAL CONSIDERATIONS $16,000.00 - $16,000.00 - - 0% $16,000.00
14.01 - New Interior Rail
$16,000.00 - $16,000.00 - - 0% $16,000.00
99 - CONTRACTING COSTS $103,469.47 $1,351.35 $104,820.82 $13,099.01 $13,099.01 12% $91,721.81
99.01 - Contracting Fee, Overhead & Profit
$103,469.47 $1,351.35 $104,820.82 $13,099.01 $13,099.01 12% $91,721.81
Totals $864,716.20 $11,746.35 $876,462.55 $113,860.65 $113,860.65 13% $762,601.90
Original Cost Control Estimate
$864,716.20
Total Changes to Work
$11,746.35
Revised Estimate
$876,462.55

Current Changes to Work

Changes introduced in DRAW 01
Category Type Description Schedule Fee Amount
02.09 - Project Liability Insurance DD Cost of the Work 0 days Yes $10,000.00
13.01 - Roof DD Cost of the Work 0 days Yes $395.00
99.01 - Contracting Fee, Overhead & Profit NA CALCULATED PER SIGNED CONTRACT 0 days - $1,351.35
Total Changes $11,746.35

Breakdown by Change Type

Overall changes impacting cost & schedule
Change Type Code Description # Days Cost
OWNER DRIVEN OD Changes driven by Owner direction & selections 0 $0.00
DESIGN DRIVEN DD Time & Costs dictated by project Design 0 $10,395.00
MATERIAL FLUCTUATION MF Changes due to cost fluctuations in materials and commodities 0 $0.00
CONSTRUCTION DRIVEN CD Time & Costs due to Construction related changes & realizations 0 $0.00
WEATHER RELATED WE Time & Costs due to Weather Conditions experienced onsite 0 $0.00
GOVERNING DEPART DRIVEN GV Changes due to requirements set by Governing Authorities 0 $0.00
ADMIN ADJUSTMENT AA Adjustments made for Administration purposes 0 $0.00
BUDGET CHANGE BC Agreed Upon Budget Changes 0 $0.00

Draw Request Coversheet

Itemized invoices for DRAW 01 — Period ending March 16, 2026
Vendor Inv Ref Fee Amount
American Electric Service inc. 2634 Yes $5,952.50
11.01 - Electrical $5,952.50
BLC inc 1 Yes $2,000.00
02.05 - Surveying $2,000.00
Builders First Source 2180 Yes $74.78
02.01 - General Labor $74.78
Colorado Building Supply 0957 Yes $43.54
02.01 - General Labor $43.54
Colorado Building Supply 2581 Yes $2,564.57
05.01 - Rough Carpentry Materials $2,564.57
Colorado Building Supply 2789 Yes $131.65
05.01 - Rough Carpentry Materials $131.65
Colorado Building Supply 3287 Yes $1,409.34
02.07 - Finish Material Protection $1,409.34
Colorado Building Supply 3305 Yes $43.54
02.01 - General Labor $43.54
Colorado Building Supply 4641 Yes $31.57
02.08 - Winter Conditions $31.57
Colorado Building Supply 6298 Yes $23.94
02.02 - Material Delivery $23.94
Edifort LLC 3036 Yes $3,850.00
05.11 - Window $3,850.00
Ever Chacon Drywall 61 Yes $5,600.00
02.01 - General Labor $5,150.00
02.06 - Construction Waste $450.00
Griffeth Structural, LLC 1710 Yes $2,000.00
01.01 - Structural Engineering $2,000.00
JVC & KB Mechanical Contractors LLC 14391-A Yes $11,050.00
10.01 - Plumbing / MECH System $11,050.00
Leo's Roofing and Remodeling 1913 Yes $1,395.00
13.01 - Roof $1,395.00
Osprey Overhead Door inc. 2790 Yes $240.00
13.02 - Garage Door $240.00
Panoramic Doors LLC 6651 Yes $14,032.29
05.10 - Doors & Window $14,032.29
Silva Constuction 0001 Yes $19,050.00
02.01 - General Labor $19,050.00
Summit Asbestos Testing, LLC 1530 Yes $974.00
01.01 - Structural Engineering $974.00
Summit Rolloffs 4389 Yes $3,651.52
02.06 - Construction Waste $3,651.52
Western Fireplace Supply 751EA Yes $13,059.09
07.04 - Fireplaces $13,059.09
Western Fireplace Supply 9144 Yes $13,584.31
07.04 - Fireplaces $13,584.31
Current Draw Total $113,860.65

Vendor Payments Due

Draw # DRAW 01 — Amounts due to vendors and contractor
Vendor Current Draw Method Reference
American Electric Service inc. $5,952.50 Need to Process 2634
BLC inc $2,000.00 Paid by GC 1
Builders First Source $74.78 Paid by GC 2180
Colorado Building Supply $4,248.15 Paid by GC 2581, 4641, 6298, 2789, 0957, 3287, 3305
Edifort LLC $3,850.00 Paid by GC 3036
Ever Chacon Drywall $5,600.00 Paid by GC 61
Griffeth Structural, LLC $2,000.00 Paid by GC 1710
JVC & KB Mechanical Contractors LLC $11,050.00 Need to Process 14391-A
Leo's Roofing and Remodeling $1,395.00 Paid by GC 1913
Osprey Overhead Door inc. $240.00 Paid by GC 2790
Panoramic Doors LLC $14,032.29 Paid by GC 6651
Silva Constuction $19,050.00 Paid by GC 0001
Summit Asbestos Testing, LLC $974.00 Paid by GC 1530
Summit Rolloffs $3,651.52 Paid by GC 4389
Western Fireplace Supply $26,643.40 Paid by GC 9144, 751EA
Vendor Total $17,002.50
Bridgeline Custom Building $13,099.01
Total Bridgeline Custom Building above includes all Bridgeline Custom Building related Draw Items including all reimbursements as listed on Draw Detail Cover Sheet.
Current Draw Total
$113,860.65
Owner Paid Direct
$0.00
Amount Due to Vendors & Contractor
$113,860.65